This page puts the whole plan on a calendar: the five phases and their dates, what each workstream does in each month from September 2026 to December 2027, the outside approvals on the critical path, the dated events, the order in which pieces must be built, where the slack is, what is cut first if time runs out, and the checkpoints where the founder decides whether to go on. The Rollout plan says what each phase contains; this page says when.

Draft v0.1 · Last updated 17 September 2026

On this page

  1. 1. Summary
  2. 2. Month by month
  3. 3. Critical path
  4. 4. Key dates
  5. 5. Dependencies between workstreams
  6. 6. Buffer and what slips first
  7. 7. Review checkpoints

1. Summary

The plan runs in five phases. A phase is a block of weeks with one goal and a set of exit criteria: the things that must be true before the next phase starts. Every phase date on this page comes from the brief. The month-by-month split, the critical path dates and the checkpoints are worked out from those dates.

The words on this page have fixed meanings across the whole spec.

Brand
The paying customer: a company, an app or SaaS product, or an agency acting for a brand. V1 customers are indie developers, indie hackers and small SaaS companies.
Creator
The person who makes and posts content on their own social account.
Campaign
What a brand creates: a brief, a 10-item checklist, a fund and settings.
Gig
One unit of work for one creator inside a campaign: one video, one post.
Offer
A gig notification sent to a creator, who can accept or decline it.
Fund
The money a brand deposits for a campaign, held by a licensed payments partner, never by the platform itself.
Checklist
The 10 items every submission must satisfy.
CPM
The rate a creator is paid per 1,000 real views, set by audience geography, platform, category and league (see Rate cards): a floor of 20% of expected earnings releases at publish, and the rest follows views read on day 3, day 7 and day 14, up to the maximum payout, which is expected earnings, unless the brand adds an optional bonus.
Wallet
The creator's balance inside the app: Pending, Available, Paid.
Payout
Money moved from the wallet to the creator's bank account on the 30-day cycle, the 1st of every month.
Ops
The platform's own operations team: review, fraud, support.
Dispatch
The process of sending offers to creators.
Dogfood campaign
A campaign funded by Distribution Club itself, run through the normal product, to test the product and recruit creators.
PhaseStartEndWeeksGoal
Phase 0, MVP sprint7 September 202620 September 20262Ship a live web app: sign-up, real dispatch, review by hand, wallet, payouts, ops console; start the entity, bank account and every other blocker in parallel
Phase 1, Build-out while live21 September 202622 January 202718Automate the manual MVP steps while real gigs run: AI review, API reads and leagues, frame hashing, native apps once the store gates clear, Razorpay Route, Payoneer, referral automation
Phase 2, Open creator beta (worldwide)25 January 202726 March 20279Creator sign-up open worldwide; 3,000 creator sign-ups, 300 creators with a completed first gig, 10 pilot brands, 150 completed brand gigs; meet the 11 beta criteria
Phase 3, Public launch29 March 202725 June 202713Self-serve; 100 paying brands, 3,000 active creators, 2,000 completed gigs a month, $200,000 monthly fund deposits
Phase 4, Scale1 July 202731 December 202726Managed campaigns at a per-campaign platform cut of 35%, agencies, Diamond custom deals, two more platforms, the 21-category roadmap and local distribution (city targeting, Preset C) open (assumption); 400 paying brands, 15,000 active creators, 10,000 completed gigs a month

Phase 0 starts on Monday 7 September 2026 and Phase 3 ends on Friday 25 June 2027. That is 42 weeks (2 plus 18 plus 9 plus 13) with almost no gap: Phase 0 ends on Sunday 20 September 2026 and Phase 1 starts the next day, Monday 21 September 2026; every later phase still ends on a Friday with the next starting the following Monday. Phase 4 adds 26 weeks, so the whole calendar covers about 68 weeks, or 16 months. The first pilot brand campaign is funded just 2 weeks after the first day of work, on day 14 of the MVP sprint (20 September 2026), and dispatches the next morning; the wider worldwide beta with all 10 pilot brands still opens 20 weeks after the first day of work (25 January 2027), and the product opens to the public 29 weeks after it (29 March 2027).

Every phase in this timeline runs inside the V1 scope decided on 5 September 2026 (Rollout plan, section 8.7): V1 customers are indie developers, indie hackers and small SaaS companies, V1 campaigns accept only ten categories (AI tools, SaaS and web apps, developer tools, productivity apps, fitness apps, health apps, lifestyle apps, education apps, kids apps, games), and matching is by audience, not creator location, with no city targeting until Phase 4 opens local distribution.

The timeline assumes one founder through 2027, doing product, engineering, review, ops and sales, with no payroll. A chartered accountant and a lawyer help, paid per job. Hires happen only when profit pays for them: an ops reviewer once submissions pass about 100 a day, about 3,000 a month, then an engineer once monthly profit covers the salary for three months (assumption); both are named as triggers, not dates, on the Rollout plan. Nothing here depends on a specific fund-raise; the working capital of about $25,000 to $35,000 the Scenarios page models is what covers the founder through the dip, not a raise. If a hire trigger is not crossed on schedule, the Phase 1 build-out weeks stretch first; section 6 says what gives way.

1.3 The MVP sprint, 7 to 20 September 2026

Phase 0 is not six weeks of preparation before anything is built; it is a two-week sprint that ships the product itself, with a real gig dispatched to a real pilot brand starting the next phase (brief section 28). The day-by-day build is below, grouped the way the brief groups it; the reasoning behind each manual step and every blocker's lead time are on the MVP in two weeks page.

DaysDatesBuildPhase
1 to 27 to 8 September 2026Payment flow validated end to end with a real small transfer (brand pays through Cashfree or Razorpay, funds held by Route or the dated fallback, one creator paid through RazorpayX, one abroad through Payoneer if available) before the data model, double-entry ledger and auth (Google sign-in, phone one-time code) are builtPhase 0, MVP sprint
3 to 59 to 11 September 2026Creator sign-up and handles, availability hours, league set by hand, brand campaign form and fund depositPhase 0, MVP sprint
6 to 812 to 14 September 2026Dispatch engine (candidate list, waves, 30-minute expiry) and offer notifications (WhatsApp or SMS and email, web push)Phase 0, MVP sprint
9 to 1015 to 16 September 2026Submission upload, review form, approved package, link check, floor releasePhase 0, MVP sprint
11 to 1217 to 18 September 2026Wallet, payout batch export, brand dashboard, ops console tablePhase 0, MVP sprint
1319 September 2026Dogfood on the founder's own account and the 20 friendly-creator accounts, the first dogfood gigPhase 0, MVP sprint
1420 September 2026Fixes from dogfood; first pilot brand campaign fundedPhase 0, MVP sprint ends

The first real gig dispatches the next morning, Monday 21 September 2026, the first day of Phase 1, Build-out while live (section 3). Every blocker with a lead time longer than two weeks, the Indian entity and bank account, GST registration, the Razorpay account and Razorpay Route, RazorpayX or Cashfree Payouts, Payoneer Mass Payouts, the WhatsApp Business API, the Google Play and Apple developer accounts, and the four platform API applications, starts on 7 September 2026 alongside this build and is detailed in section 3.

2. Month by month

For each month this section lists what five workstreams are doing and one month-end checkpoint: the single thing that must be true by the last working day of the month. The workstreams are Engineering, Product and design, Supply (creators) and Demand (brands), all the founder's own work, and Ops and legal (the founder, with the accountant and the lawyer paid per job). Phase contents come from the brief; the month-end checkpoints and the spread of Phase 4 work across July to December are planning choices made on this page (assumption).

2.1 September 2026 (Phase 0, MVP sprint, then Phase 1 build-out begins)

2.2 October 2026 (Phase 1 build-out)

2.3 November 2026 (Phase 1 build-out)

2.4 December 2026 (Phase 1 build-out)

2.5 January 2027 (Phase 1 build-out, final stretch, then Phase 2 week 1)

2.6 February 2027 (Phase 2, weeks 2 to 5)

2.7 March 2027 (Phase 2 weeks 6 to 9, then Phase 3 week 1)

2.8 April 2027 (Phase 3, weeks 1 to 5)

2.9 May 2027 (Phase 3, weeks 6 to 9)

2.10 June 2027 (Phase 3, weeks 10 to 13)

2.11 July 2027 (Phase 4 starts Thursday 1 July; spread proposed)

The brief gives Phase 4 a list of items between 1 July and 31 December 2027 with no order inside it. The spread below (proposed) puts money and pricing changes first, new platforms in the middle, and language and market research last, so each item has data from the one before.

2.12 August 2027 (Phase 4; spread proposed)

2.13 September 2027 (Phase 4; spread proposed)

2.14 October 2027 (Phase 4; spread proposed)

2.15 November 2027 (Phase 4; spread proposed)

2.16 December 2027 (Phase 4 ends Friday 31 December; spread proposed)

3. Critical path

The critical path to the two-week MVP is short, because everything a platform API or an app store would normally do is done by hand at launch (brief section 28). The chain that cannot be shortened and that the 21 September 2026 launch waits on is: the entity and bank account, then the Razorpay pay-in account, then a way to pay creators, either Razorpay Route or its RazorpayX fallback, plus the legal papers. Every other outside approval below, the four platforms' APIs, the two app stores, is a Phase 1 build-out item: it makes something automatic that already works by hand, and none of it moves the 21 September 2026 date. Most of these items are outside the founder's control, which is why they all start on 7 September 2026, the first day of Phase 0. The Dependencies page describes each outside service; this section gives only the dates.

Four items concern the social platforms, and none of them sit on the two-week launch path. To read view counts automatically, the app needs a read permission from each platform; to post automatically, it needs a separate publishing permission. Meta grants Instagram insights (reading views) and, separately, publishing, both through Meta App Review. Google runs an API compliance audit before an app can read YouTube Analytics, and a separate upload audit before it can post automatically. TikTok audits an app separately for reading view counts (through the Display API or a video query) and for posting through its Content Posting API. X sells API access in paid monthly tiers covering both reading and posting, so there is a purchase, not a split audit. The brief puts each of these audits at 2 to 8 weeks; the exact steps should be verified against each platform's current documentation. Because the MVP reads views by hand on day 3, day 7 and day 14 of each gig, and creators post themselves with the founder verifying the link by hand, none of these six approvals block the first dispatch on 21 September 2026. They are Phase 1 build-out items instead: each platform's reads and leagues switch from a manual check to an automatic one as its read permission arrives, and each platform's posting switches from creator-posted to automatic as its publishing permission arrives, targeted for Phase 3.

ItemStart byExpected timeMust be done byWhat it blocks
Entity and bank account7 September 20267 to 15 working daysIdeally by 20 September 2026 (day 14)Every brand fund deposit; until it exists, only dogfood gigs, paid from the founder's own account
GST registrationOnce incorporation is filed3 to 7 working days after incorporationBefore the first brand invoiceThe first pilot brand's invoice
Razorpay account (pay-in)7 September 20261 to 3 working days after KYCBefore 21 September 2026Collecting brand payments from day one of Phase 1
Razorpay Route7 September 2026, during onboarding1 to 2 weeksIdeally by 21 September 2026, else the dated RazorpayX fallback with the lawyer's sign-offLaunch blocker: holding and splitting brand funds to creators without the platform touching the money, so gigs launch as a marketplace with GST on the platform's 20% cut only rather than as the principal with GST on the full price (Payments)
RazorpayX (Cashfree Payouts is closed to proprietorships, confirmed 12 September 2026)7 September 20262 to 5 working daysBefore 1 October 2026, the first payout runPaying Indian creators by UPI, IMPS or NEFT
Bulk payouts abroad (Payoneer India is receive-only and PayPal India has no bulk Payouts, confirmed 16 and 17 September 2026; Karbon or PayPal one at a time in the meantime)7 September 2026Open: RazorpayX Global Payouts reply or a foreign subsidiaryWithin Phase 1 build-outPaying creators outside India; until live, their wallet holds the balance
WhatsApp Business API7 September 20261 to 2 weeks for verification, then 1 to 3 days for the APIWithin Phase 1 build-outOffer delivery by WhatsApp; SMS and email are the day-one channels
Meta App Review, insights (read Instagram views)7 September 20262 to 8 weeksWithin Phase 1 build-outAutomatic Instagram view tracking and leagues; build-out only, since the MVP reads views by hand
Meta App Review, publishing (post to Instagram Reels)7 September 20262 to 8 weeksWithin Phase 3 (April to June 2027)Automatic Instagram posting only; build-out
Google API compliance audit, analytics side (read YouTube views)7 September 20262 to 8 weeksWithin Phase 1 build-outAutomatic YouTube view tracking and leagues; build-out only
Google API compliance audit, upload side (post to YouTube)7 September 20262 to 8 weeksWithin Phase 3 (April to June 2027)Automatic YouTube posting only; build-out
TikTok read access (Display API or video query for views)7 September 20262 to 8 weeksWithin Phase 1 build-outAutomatic TikTok view tracking and leagues; build-out only
TikTok Content Posting API audit7 September 20262 to 8 weeksWithin Phase 3 (April to June 2027)Automatic TikTok posting only; build-out
X paid API tier7 September 2026DaysWithin Phase 1 build-outAutomatic X view tracking; build-out only, since the MVP reads X's public counts by hand
Apple and Google developer accounts7 September 2026Google 14-day closed test (personal) or 1 to 2 weeks of organisation verification; Apple 1 to 10 days to enrol plus 2 to 5 days for first review; verify against current documentationWithin Phase 1 build-outThe native apps only; build-out, since the MVP launches as a web app
App store review (iOS and Android)Submit once the store gates clearAbout 1 weekWithin Phase 1 build-out, targeted by 22 January 2027The native app launch only; build-out
Legal documents (terms, privacy policy, creator and brand agreements, disclosure policy)7 September 2026About a weekBefore 21 September 2026, the first dispatchThe first dispatch and every sign-up
Pilot brand letters of intent7 September 2026Ongoing through Phase 1 build-out1 signed by 20 September 2026 (day 14); 10 signed by 22 January 2027The pilot brands' beta campaigns

The lead times for the entity, GST, Razorpay, Route, RazorpayX or Cashfree, Payoneer and the WhatsApp Business API come from brief section 28. Everything on this list starts on 7 September 2026, whether it blocks the 21 September launch or not, because none of it can be sped up once it starts. The four platform APIs, the two app stores and the developer accounts are marked build-out because none of them are needed for the two-week launch: the MVP reads views by hand, verifies posts by hand, and ships as a web app, so these approvals only replace a manual step with an automatic one once they land, inside Phase 1 build-out (21 September 2026 to 22 January 2027) for the read and store items, and inside Phase 3 (April to June 2027) for the publishing audits.

If a platform's read permission is late. Because view reads and leagues are already done by hand at MVP, a late platform API approval does not threaten the 21 September 2026 launch or the 25 January 2027 beta date; it only delays that platform's move from a manual read to an automatic one. If a platform's read permission is still pending when Phase 1 build-out ends on 22 January 2027, ops keeps reading its public view counts by hand (YouTube and X give these without a connected account) or by creator screenshot (Instagram and TikTok need the creator's connected account), and that platform's automation lands in a later release once the permission arrives (assumption). None of this affects posting: automatic posting is a Phase 3 addition on every platform, since creators post the approved package themselves from launch and the platform verifies the posted link, by hand at MVP and by frame hash once that build-out item ships (Rollout plan, section 4).

4. Key dates

Every dated event in the plan, in order. Payout runs are included because they are fixed to the 1st of every month and never move.

  1. Monday 7 September 2026: Phase 0, MVP sprint starts. All four platform applications submitted; the entity, Razorpay, Razorpay Route, RazorpayX or Cashfree, Payoneer and the WhatsApp Business API applications begin; Apple and Google developer accounts opened; legal drafting begins.
  2. Saturday 19 September 2026: day 13 of the sprint. First dogfood gig, on the founder's own account and the 20 friendly-creator accounts.
  3. Sunday 20 September 2026: day 14 of the sprint, Phase 0 ends. First pilot brand campaign funded.
  4. Monday 21 September 2026: Phase 1, Build-out while live starts. First real gig dispatched.
  5. Thursday 1 October 2026: first payout run, paying dogfood and pilot-brand earnings since 21 September.
  6. Sunday 1 November 2026: payout run.
  7. Tuesday 1 December 2026: payout run.
  8. Friday 1 January 2027: payout run.
  9. Friday 22 January 2027: Phase 1 build-out ends. Checkpoint on automated checklist scoring, API reads and leagues on at least three platforms, frame-hash matching, both native app submissions (or a named reason either store gate has not cleared), Razorpay Route (or the RazorpayX fallback), Payoneer, and referral automation.
  10. Monday 25 January 2027: beta starts. App store review done if the native apps have shipped; the 10 pilot brands onboarded by hand.
  11. Monday 1 February 2027: payout run, the fifth since October, now including the wider beta. "Payout day" dogfood campaign dispatched.
  12. Friday 26 February 2027: mid-beta checkpoint.
  13. Monday 1 March 2027: payout run.
  14. Friday 26 March 2027: beta ends. Phase review against the 11 beta criteria; go or no-go.
  15. Monday 29 March 2027: public launch. Self-serve sign-up; dogfood budget rises to $5,000 a week; automatic posting begins rolling out platform by platform through June as each publishing permission is approved.
  16. Thursday 1 April 2027: payout run.
  17. Saturday 1 May 2027: payout run.
  18. Friday 14 May 2027: mid-launch checkpoint.
  19. Tuesday 1 June 2027: payout run.
  20. Friday 25 June 2027: Phase 3 ends. Phase review against the Phase 3 targets.
  21. Thursday 1 July 2027: Phase 4 starts. Payout run.
  22. Sunday 1 August 2027: payout run.
  23. Wednesday 1 September 2027: payout run.
  24. Friday 1 October 2027: payout run.
  25. Monday 1 November 2027: payout run.
  26. Wednesday 1 December 2027: payout run.
  27. Friday 31 December 2027: Phase 4 ends. Phase review against the Phase 4 targets and the new language and payout-rail additions.

Payout runs happen on the calendar date even when the 1st is a weekend, as on 1 May and 1 August 2027; the batch is automatic and the money reaches bank accounts on the partner's next settlement day (assumption). Only creators with completed payout setup and an Available balance of at least $20 are included; smaller balances roll over. Each payout run also triggers that month's league recalculation, since a creator's league is set by their median views over the last 90 days. The founder runs each batch from the ops console, as described on the Dogfooding page.

5. Dependencies between workstreams

Each line is a hard order: the first item must be finished and tested before the second can be built or run. The two-week sprint follows this same order, day by day (section 1.3): days 1 to 2 are the ledger and auth, days 3 to 5 are sign-up and campaign funding, days 6 to 8 are dispatch and offers, days 9 to 10 are upload, review, the approved package and posting, and days 11 to 12 are the wallet and the payout batch. Several items below describe the automated version of a step; at MVP that step is done by hand instead, and the Phase 1 build-out (Rollout plan, section 4) is what turns it automatic, in the same order.

  1. The Razorpay pay-in account must finish before campaign funding, because the fund is collected there, either through Razorpay Route or, until that is approved, the entity's own Razorpay account paying out through RazorpayX.
  2. Social connect (the OAuth login for Instagram, YouTube, TikTok and X) must finish before the eligibility check and expected-earnings calculation can read each account's median views automatically from the platform's API; at MVP a creator's handle is entered by hand and ops sets the league from the last 10 posts, so this item is Phase 1 build-out, not a launch dependency.
  3. Funding must finish before dispatch, because dispatch starts only when the fund is received and the brand-safety check is done.
  4. Dispatch must finish before offers, because an offer is what dispatch sends: 2 to 6 offers per open slot, adapting to the recent acceptance rate for that category and league, each expiring after 30 minutes, in waves for up to 48 hours.
  5. Upload must finish before review, because review, whether the founder reading it by hand at MVP or the automated pass added in the build-out, needs the uploaded video first.
  6. Review must finish before the approved package, because only a submission with all 10 items passed is turned into the exact file and caption the creator is given to post.
  7. The approved package must finish before creator posting, because the creator can only post once given the reviewed file and caption.
  8. Creator posting must finish before the link check, because the platform, or the founder by hand at MVP, can only check a posted link once the creator has posted it.
  9. The link check must finish before tracking, because tracking starts from the post's own publish time once the post is confirmed to match the approved file, by eye at MVP and by frame hash once that build-out item ships.
  10. Tracking must finish before earnings release, because pay is released from view counts read on day 3, day 7 and day 14, by hand at MVP and automatically once each platform's read permission lands.
  11. The ledger must finish before the wallet, because every wallet balance is a sum of ledger entries.
  12. The wallet and payout setup (identity, PAN and bank details, tax form) must finish before the payout batch, because the batch pays only Available balances to verified bank accounts.
  13. Dogfood (day 13 of the sprint) must finish before the first pilot brand's gig (day 14), because the founder must have completed a real gig with real money first.
  14. The beta criteria must be met before the public launch, because self-serve removes the hand-holding by the founder that covers gaps in the beta.

6. Buffer and what slips first

A buffer is time in the plan that is not needed if everything goes right. This plan has two buffers, a cut list, four fixed promises and one rule.

6.1 Where the buffer is

6.2 What slips first

If time runs out, features are cut in this order, taken from the cut list on the Rollout plan page. Each cut is a delay to a later weekly release, not a removal.

  1. Automatic posting. Creators post the approved package themselves at MVP, so switching a platform to automatic posting waits for that platform's publishing permission.
  2. X view tracking automation. Views are already read by hand for every platform at MVP; if X's paid API tier is delayed, ops keeps reading its public counts by hand past the end of Phase 1 build-out, with no effect on the launch or the beta date.
  3. Preset F "Clipping".
  4. Custom checklists. Brands keep editing up to 3 of the 10 items until then.
  5. Instant payout at 2%. Creators keep the monthly payout on the 1st.
  6. Volume pricing. Brands stay on pay as you go, with the platform keeping 20% of every deposit at once.
  7. Non-English product languages (Spanish, Hindi, Portuguese) and the extra local payout rails.

6.3 What never slips

These four are promises to creators and brands, not features. If the founder cannot keep one at the current volume, dispatch is paused until it can, rather than the rule being bent (assumption).

6.4 Rule for starting a phase

A phase does not start until the previous phase's exit criteria are met. If they are not met on the review date, the phase is extended one week at a time, the review is repeated, and every later date on this page moves by the same number of weeks (assumption). The one exception is Phase 4, which starts on 1 July 2027 regardless of the Phase 3 result, because its content is a list of additions that can be reordered rather than a gate (assumption). If Phase 3 misses its targets, the Phase 4 list is cut from the bottom, starting with the non-English product languages and the API for agencies (assumption).

7. Review checkpoints

A checkpoint is a dated review by the founder where one question is answered with numbers from the ops console and the brand dashboard, and one decision is written down. There are eight: one at the end of each phase, one mid-beta, one mid-launch, and one added a fortnight into Phase 1 to check the core loop is proven (assumption). The beta criteria are listed in full on the Rollout plan page; the risks each checkpoint watches are on the Challenges page.

DateCheckpointQuestion to answerDecision
Sunday 20 September 2026Phase 0 endIs the web app live, is the ops console working, are the legal papers live, has the payment flow been validated end to end with a real small transfer, and has the day 13 dogfood gig completed and the day 14 pilot brand campaign been funded?Dispatch the first real gig on 21 September, or delay it a day at a time and name what is missing.
Sunday 4 October 2026Core loop proven? (end of the first month, assumption)Has the MVP success test been met: at least ten posts live and 200,000 to 250,000 views for a US developer audience within 14 days of the pilot brand's $1,000 deposit on 20 September, with clicks reported?Move from manual operation toward the Phase 1 build-out automation on schedule, or hold automation and fix the core loop first (assumption).
Friday 22 January 2027Phase 1 build-out endIs automated checklist scoring live, are API reads and leagues live on at least three platforms, is frame-hash matching live, are both native apps submitted or is there a named reason not, and are Razorpay Route (or the RazorpayX fallback), Payoneer and referral automation all working?Start the beta on 25 January regardless, since it runs on the web app either way; note any build-out item still catching up.
Friday 26 February 2027Mid-betaAre fill rate (70% within 2 hours), on-time submission (80%) and the review SLA (90% automated result within 24 hours, decision within 48 hours) on track, and have the payout runs since October, including the one that folded in the wider beta on 1 February, been clean?Tune dispatch, leagues and the dogfood budget; confirm or postpone launch preparation.
Friday 26 March 2027Phase 2 endAre all 11 beta criteria met, including 40% brand repeat, 50% creator retention and fraud under 2%?Public launch on 29 March, or extend the beta one week at a time.
Friday 14 May 2027Mid-launchAre self-serve brands funding campaigns without the founder's help, and are brands, creators and deposits on a line to 100, 3,000 and $200,000 by 25 June?Shift effort between supply and demand; keep or cut Preset F and custom checklists from Phase 3.
Friday 25 June 2027Phase 3 endWere the targets hit (100 paying brands, 3,000 active creators, 2,000 completed gigs a month, $200,000 monthly deposits), and is the contribution margin moving toward 65%?Confirm the Phase 4 list and order; name what is cut if targets were missed.
Friday 31 December 2027Phase 4 endWere the targets hit (400 paying brands, 15,000 active creators, 10,000 completed gigs a month), and are the Spanish, Hindi and Portuguese product languages and the extra local payout rails live and reaching new countries?Confirm the 2028 plan: which countries to prioritise next for local payout rails and languages.

When a checkpoint moves a date, this page is reissued as the next draft version with the new dates, so every other page still points at one calendar (assumption). The assumptions on this page are collected on the Assumptions page.